Endeavour Silver Sees Initial Capital Costs Jump 22% At Terronera

Endeavour Silver (TSX: EDR) has seen expected costing at its Terronera project under development rise dramatically. The firm this morning provided a progress update to the project, indicating that expected costing has risen over 22%.

Total direct and indirect costing at the project has risen from $271 million to $332 million, a jump of $61 million. The increase was split between direct cost increases of $31.8 million and indirect cost increases of $29.2 million, which was partially offset by a decrease in contingencies.

On the direct side of things, mining costs have increased by $16 million, which is largely attributed to the delays in commissioning the lower platform facilities, as well as increased waste rock disposal costs. The processing plant is also over budget by $13.2 million, which is blamed on additional blasting required for lower platform excavation, extra work for expediting steel fabrication, and extra materials for the tailings facility, among other items.

Indirect costs meanwhile increased due to additional engineering, construction management, and the addition of several support buildings that were not originally planned, as well as a result of a larger workforce required than originally anticipated.

Development at Terronera is said to now be 89.4% complete, with Endeavour currently targeting early in Q2 for full system commissioning to begin on site. Operational guidance is slated to be released as construction approaches wet commissioning.

“Dry commissioning is advancing well on the Upper Platform and we’re completing final installations and the last of the punch list items. Our team’s efforts are concentrated on timely completion of the Lower Platform where structural steel is advancing to install the tailing filters. We’re focused on maintaining our construction schedule and momentum to have Terronera ready for full commissioning in early Q2 2025,” commented Don Gray, COO of Endeavour Silver.

Endeavour Silver last traded at $5.85 on the TSX.


Information for this briefing was found via Sedar and the companies mentioned. The author has no securities or affiliations related to this organization. Not a recommendation to buy or sell. Always do additional research and consult a professional before purchasing a security. The author holds no licenses.

Video Articles

Mergers Set the Stage for Uranium’s Growth Cycle | Forum-Baselode Merger

The Goal is Gold Production as Soon as Possible! | Gordon Robb – ESGOLD Corp.

Snowline Gold: The Multi Billion Dollar Valley PEA

Recommended

First Majestic Produces 7.9 Silver Equivalent Ounces In Q2, Lifts Production Guidance

Antimony Resources Drills 4.17% Antimony Over 7.4 Metres At Bald Hill

Related News

Endeavour Silver Beats BMO’s Production Estimates By 30%

Last week, Endeavour Silver Corp. (TSX: EDR) announced their third quarter production highlights. For the...

Thursday, October 14, 2021, 03:20:00 PM

Endeavour Silver Q4 Earnings: Market Loves The Results

Three weeks ago we had a request to cover Endeavour Silver’s (TSX: EDR) fourth quarter...

Sunday, March 16, 2025, 12:25:00 PM

Endeavour Silver Intersects 2,914 G/T Silver Equivalent Over 0.89 Metre At Parral Project

Endeavour Silver Corp. (TSX: EDR) announced today the latest drill results from the ongoing exploration...

Thursday, December 16, 2021, 12:36:00 PM

VanGold Acquires El Cubo Mine & Mill From Endeavour Silver For US$15.0 Million

VanGold Mining (TSXV: VGLD) announced that it has entered into a definitive agreement with Endeavour...

Wednesday, March 17, 2021, 07:57:17 AM

Endeavour Silver Forecasts Production Midpoint Of 7.45 Million Silver Equivalent Ounces In 2025

Endeavour Silver (TSX: EDR) has released its guidance for 2025, with the company calling for...

Wednesday, January 15, 2025, 09:48:37 AM