Amex Gold Mining (TSXV: AMX) has advanced the main access ramp at its Perron gold project to 200 metres, and construction is now underway on the power line meant to carry the site from its bulk sample into a planned first phase of mining.
Development has sped up noticeably. In its September 21 update, the company said the decline had only just passed 75 metres, so 125 metres have been added in under two months. Amex said the work remains on schedule with its construction plans.
The ramp is heading toward the high grade Champagne Zone as part of a fully funded 40,000 tonne bulk sample program. The program is designed to test underground mining conditions, grade continuity, dilution, mining recovery and metallurgical performance.
The power line has moved past clearing and into construction, and the first pole is now in the ground. The 25-kV line runs 6.5 kilometres and will connect Perron to the existing grid with 3 MW of capacity. That’s enough to supply both the bulk sample and the Phase 1 operation set out in the feasibility study Amex released in April. Once the line is energized, the site is expected to switch to hydroelectric power for its surface and underground facilities and rely less on diesel generators.
The rest of the site is being built out alongside the ramp. The structure of the mechanical garage is complete, and it will handle maintenance and servicing of the underground fleet. The permanent underground ventilation system is also installed and will supply airflow as development pushes toward the bulk sample areas. Amex said most of the bulk sample site facilities are now up and close to completion.
“Our team continues to make excellent progress at Perron, advancing the underground ramp while simultaneously progressing several major infrastructure projects,” said President and CEO Victor Cantore. “Importantly, we are not simply building infrastructure for the bulk sample program but investing in facilities that will also support our future Phase 1 mining operation.”
The update repeatedly makes the point that the work serves two purposes. Amex is sizing the power line and site facilities for Phase 1 now, which it expects will spare it another major round of electrical infrastructure spending once mining moves past the bulk sample stage.
Perron covers 183 contiguous claims over 65.72 square kilometres in northern Quebec. Together with the company’s neighbouring holdings in Ontario, the land package totals 570.94 square kilometres.
Amex Gold last traded at $2.94 on the TSX Venture.