IAMGOLD Declares Commercial Production At Cote Gold Mine

IAMGOLD (TSX: IMG) has declared that it has achieved commercial production at the Cote Gold Mine. The declaration implies that the mine has successfully operated at an average of 60% of nameplate capacity for a consecutive 30 days, and follows the first gold pour that occurred back in March.

The advent of commercial production implies that the operation has been been operating at a throughput of roughly 21,600 tonnes per day. IAMGOLD has said that it aims to exit the year operating at 90% of nameplate capacity.

“With commercial production behind us we continue to focus on improving plant availability towards our goal of Côté exiting the year at 90% of nameplate throughput. Further, in May we completed our equity financing which has positioned us well to repurchase the 9.7% interest in Côté this November and return to 70% ownership thereby gaining more exposure to this foundational and keystone asset for the benefit of all our stakeholders,” commented Renaud Adams, CEO of IAMGOLD.

The company has said that major equipment has demonstrated the ability to operate at nameplate capacity or higher, with the firm in the second quarter focusing on testing processing circuits to handle nameplate loads.

The Cote Gold Mine, currently 60% owned by IAMGOLD and 40% owned by Sumitomo Metal Mining, is expected to produce 495,000 ounces of gold for the first five years of production, with the mine estimated to have a total mine life of 18 years.

IAMGOLD last traded at $5.69 on the TSX.


Information for this briefing was found via Sedar and the sources mentioned. The author has no securities or affiliations related to this organization. Not a recommendation to buy or sell. Always do additional research and consult a professional before purchasing a security. The author holds no licenses.

Video Articles

Moon River Moly: The Davidson Moly-Copper-Tungsten PEA

Integra: The DeLamar Heap Leach Feasibility Study

Highlander Silver: The Saviour Of Bear Creek Mining

Recommended

Mercado Minerals Launches Two Phase Geophysical Program At Copalito Project

Altamira Gold Drills 6.1 g/t Gold Over 2.3 Metres At Cajueiro Central, Begins Testing Two New Targets

Related News

IAMGOLD Drills 19 Meters At 5.15 g/t Gold In Nelligan Project

IAMGOLD Corporation (TSX: IMG) has released new assay results from its 2024 drilling program at...

Wednesday, October 23, 2024, 08:46:00 AM

IAMGOLD Records US$297.4 Million In Revenue For Q1 2021

IAMGOLD Corporation (TSX: IMG) reported today its financial results for Q1 2021, highlighting revenue of...

Tuesday, May 4, 2021, 10:19:00 AM

Market Movers: IAMGOLD Sheds 25% On Continued Costing Struggles At Cote Gold Project

IAMGOLD Corp (TSX: IMG) is one of the largest movers in the Canadian markets today,...

Wednesday, May 4, 2022, 04:20:24 PM

IAMGOLD Resumes Production At Rosebel Following Union Work Stoppage Due To COVID-19 Infections

IAMGOLD Corp (TSX: IMG) released to the market late Friday night that it has resumed...

Sunday, July 26, 2020, 11:45:00 AM

IAMGOLD To Acquire Nelligan Project Joint Venture Partner Vanstar Mining For $31.1 Million

IAMGOLD (TSX: IMG) has apparently determined it is easier to just buy a joint venture...

Tuesday, December 5, 2023, 09:19:24 AM