Queensland’s claim that a proposed A$32 billion AI data centre will lower household electricity bills now faces a numerical test, after an opposition lawmaker demanded official forecasts for the project’s power demand and its impact on consumers.
In a parliamentary question, Labor MP Mick de Brenni asked Treasurer and Energy Minister David Janetzki to disclose projected electricity consumption at each stage of Western Downs Digital Park, the additional generation needed to supply it, and the expected annual dollar change in a typical household’s bill. He also sought a guarantee that the development would not increase electricity costs.
The question cited an independent estimate of up to 47,000 megawatt-hours of daily consumption when all four stages are complete. ABC News previously reported that the project’s maximum power draw could reach 2.16 gigawatts, potentially adding roughly one-quarter to Queensland’s current daily electricity requirements.
Premier David Crisafulli promoted the deal in September, saying, “This is a major win that will deliver more jobs, put more energy into Queensland’s grid and drive down power prices for Queenslanders.”
Developer Zerra DC says the project will buy power from existing generators and new facilities that will add more electricity to the market than the campus consumes. Its website claims this arrangement would put downward pressure on prices.
It does not, however, provide a quantified household-bill saving or a publicly verifiable generation schedule in the material reviewed.
The economic claim is under scrutiny as the approval process absorbs overwhelming public resistance. Reuters reported that 595 of 598 submissions opposed the project or requested a delay, compared with two in support and one neutral.
ABC Southern Queensland separately reported 627 council submissions, also identifying only two supporters. The totals differ, and neither count should be treated as the number of distinct local residents.
The government’s planning policy presents another point of tension. Queensland has said data centre deals need the backing of communities and councils, while proposing to centralize approvals.
ABC also reported in October that Zerra DC had sought a designation allowing the state’s coordinator-general to take over the decision from the local council.
Anthropic, which began trading publicly on November 19, has agreed to lease space in the development, subject to regulatory approvals.