Nickel Creek Platinum has ended its 2026 drilling campaign in Yukon without reaching the underground target it set out to test, leaving the company facing another financing requirement after raising approximately $2.43 million through share placements tied partly to exploration over the past year.
The disclosure creates a gap between the capital raised and the geological evidence delivered. Nickel Creek reported no significant drilling results from the program at its Wellgreen site within the Nickel Shäw project. The company has also not disclosed how much of the financing it actually spent on drilling.
The stock was already under pressure before the announcement. Nickel Creek closed at $0.91 on Wednesday, down approximately 31% from its September 30 close of $1.32.
Nickel Creek’s financing effort began well before this season. The company closed two tranches totaling about $1.78 million in November and December 2025, with proceeds allocated to the proposed drilling campaign, project maintenance, permitting, and corporate purposes.
On October 29, 2026, Nickel Creek announced a further $654,999 placement. Electrum Strategic Opportunities Fund, an existing major shareholder, subscribed for 300,000 common shares at $1.35 each, contributing $405,000 while other investors purchased 166,666 flow-through shares at $1.50, generating approximately $250,000.
The placement price paid by Electrum was approximately 33% above Nickel Creek’s Wednesday market close.
The flow-through proceeds were designated for qualifying exploration expenses in 2026 or potential 2027 activities. Common-share proceeds were also earmarked for permitting, holding costs, and working capital.
Drill rig delays and difficult ground
Nickel Creek said the program started late because of limited drill-rig availability. Its first hole was abandoned amid difficult ground conditions. The second was stopped because worsening weather raised safety concerns.
Neither reached the intended depth of roughly 600 metres, where earlier geophysical work identified an anomaly.
The company left casing in the second hole so it could potentially resume drilling there.
“We continue to believe that this deep target warrants testing and will look to continue drilling, subject to securing additional financing,” CEO Stuart Harshaw said.
Nickel Creek has not established whether the anomaly contains economically recoverable minerals.