Agnico Eagle Halts Mining In Barnat Pit After Wall Failure at Canadian Malartic

Agnico Eagle Mines (TSX: AEM) has suspended mining at the Barnat open pit at its Canadian Malartic complex in Quebec after a section of the pit’s north wall gave way.

The company said a rock mass movement struck the wall on July 1 and that no one was hurt. There was no equipment damage or environmental impact. Mining in the pit was halted as a precaution while technical teams assess the ground.

The failure is said to have occurred in an area that was previously flagged for weaker geological structures and placed under enhanced geotechnical monitoring, including safety exclusion zones. Agnico said the affected zone was being watched under its standard mine-planning and safety protocols when the movement happened.

Selkirk Copper Mines — sponsored Sponsored · Selkirk Copper Mines

Crews are now running a detailed stability assessment to map out a safe restart, though the company has not set a firm timeline.

The processing plant will keep running in the meantime. Agnico plans to feed the mill low grade ore from existing stockpiles in place of the Barnat material, softening the near term hit to output.

In terms of impact, Agnico still expects roughly 845,000 ounces of gold production in the second quarter, slightly ahead of plan. The damage lands in the back half of the year, with the company estimating a reduction of 60,000 to 80,000 ounces at Canadian Malartic overall. Full year output is now expected near the low end of its 3.3 million to 3.5 million ounce guidance range.

The larger impact is to occur over the coming years. Barnat was scheduled to be mined out by early 2029, and Agnico now sees the event trimming as much as 150,000 ounces annually in both 2027 and 2028 from production plans, pending its review.

Notably, the company said the neighbouring Odyssey underground mine is unaffected, and its plan to lift Canadian Malartic to 1 million ounces a year in the early 2030s remains intact.

Updated guidance will accompany second quarter results on July 29.

Agnico Eagle last traded at $220.36 on the TSX.

Information for this briefing was found via the sources and the companies mentioned. The author has no securities or affiliations related to this organization. Not a recommendation to buy or sell. Always do additional research and consult a professional before purchasing a security. The author holds no licenses.
Video Articles

8 Mining Stocks Our Viewers Asked Us to Review | Sept 14th-18th

Canada Is Finally Fast-Tracking New Mines | John Passalacqua – First Phosphate

Gold & Silver Just Added $2 Billion to This Project | Aya Gold – Bourmadine PEA

Recommended

Japan Gold Lands $50 Million in Committed Capital Through Solidcore Alliance

Blue Jay Gold Produces 66.9% Antimony Concentrate at 93.9% Recovery From Becker-Cochran

Related News

Perpetua Secures $255 Million In Funding From Agnico Eagle And JPMorganChase

Perpetua Resources (TSX: PPTA) has secured two new major investors following the launch of construction...

Monday, October 27, 2025, 08:35:27 AM

Agnico Eagle Takes 14.99% Stake In Collective Mining With $63.4 Million Investment

Collective Mining (TSX: CNL) has managed to secure a substantial investment from Agnico Eagle Mines...

Friday, March 14, 2025, 08:21:38 AM

Cadillac Mines Upsizes IPO to $385 Million as Agnico Eagle Takes 11% Position

Agnico Eagle Mines (TSX: AEM) has agreed to buy 8.7 million common shares of Cadillac...

Friday, July 24, 2026, 09:16:54 AM

Wallbridge Lands $56 Million from Agnico Eagle and Waratah, Plans Rebrand to Sunday Lake Gold

Wallbridge Mining Company (TSX: WM) has secured cornerstone backing from Agnico Eagle Mines and Waratah...

Wednesday, May 20, 2026, 08:05:03 AM

Agnico Eagle To Acquire O3 Mining For $1.67 A Share In Cash

Agnico Eagle Mines (TSX: AEM) is set to expand its Canadian Malartic Complex in Quebec...

Thursday, December 12, 2024, 08:08:11 AM