First Mining Gold (TSX: FF) has secured provincial environmental assessment approval for its Springpole gold project in northwestern Ontario. That clears the last major regulatory hurdle between the company and a construction decision on one of the largest undeveloped gold projects in the country.
Todd McCarthy, Ontario’s Minister of the Environment, Conservation and Parks, granted the approval on behalf of the province, and the Lieutenant Governor in Council confirmed it. The sign off comes less than five months after Ottawa cleared the project in June, when federal Environment Minister Julie Dabrusin issued a decision statement allowing Springpole to proceed.
The federal review had been running since 2018. It drew input from Indigenous communities, the public and several federal departments, including Fisheries and Oceans Canada and Natural Resources Canada. The conditions attached to that approval cover engineering design, aquatic and terrestrial protections, monitoring, adaptive management and consultation, and they largely follow the mitigation commitments First Mining proposed during the process.
With both levels of government now on board, and formal project agreements in place with local Indigenous communities, the company says it can now focus on building the mine.
Chief Executive Officer Dan Wilton called the approval “a defining moment in the advancement of Springpole,” and said the company can now turn years of assessment-phase planning into real progress on the ground. He also credited provincial reviewers, Indigenous partners, local municipalities and other stakeholders for their role in getting the project to this point.
First Mining is targeting completion of a definitive feasibility study in 2027, alongside project financing arrangements, with a final construction decision slated for 2028. The company is building out its construction team and has already started the planning and engineering needed for a phased build.
Phase 1 work centres on site preparation. It includes an 18 kilometre all weather access road, a construction camp, a power connection, material laydown areas and access to aggregate sources. The company has also received permits for a winter road this season to resupply the existing camp and prepare for work planned in 2027.
Springpole hosts indicated resources of 4.8 million ounces of gold and 28 million ounces of silver, with probable reserves of 3.1 million ounces of gold and 16.1 million ounces of silver as outlined in a December 2025 prefeasibility study.
First Mining Gold last traded at $0.53 on the TSX.