Quebec’s road program was already expected to fall far short of its pavement-repair targets before a summer labour dispute pushed 63 additional projects into 2027, creating another scheduling burden for a network with a $24.5 billion maintenance backlog.
In a report dated January 23, the province’s independent road-programming committee projected that planned interventions over the following two years would meet only 30% of targets measured in kilometres. It cited budget and operational constraints that left regional offices unable to schedule enough work to maintain existing pavement conditions.
The projection was not a forecast for the 63 projects now delayed. It was a warning about the scale of road maintenance the government could deliver before the strike disrupted its construction season.
The new deferral count comes from a transport ministry compilation obtained by Le Journal, which reported that the postponements cover 13 of Quebec’s 16 regions: Estrie, Capitale-Nationale, Saguenay–Lac-Saint-Jean, Chaudière-Appalaches, and Montérégie each account for eight projects, according to the outlet.
The affected work includes maintenance on the Quebec Bridge deck, repaving along Autoroute 40 at Saint-Augustin-de-Desmaures, and bridge rehabilitation on Autoroute 10 in Estrie.
More than 150 construction sites had been slowed or stopped during the engineers’ strike, according to a joint August 12 warning from three construction-industry associations. The union dispute ended that day.
The dates on which individual projects were formally moved into 2027 have not been disclosed.
A backlog that predates the walkout
Quebec’s 2026–2036 infrastructure plan valued the road network’s asset-maintenance deficit at $24.52 billion, up from approximately $22.5 billion in the previous reporting cycle.
The government attributed $1.1 billion of additional road-maintenance needs to natural deterioration and identified another $2.2 billion in road-repair needs, citing rising asphalt costs among the contributing factors.
The transport ministry told Le Journal it did not anticipate additional costs specifically attributable to the deferrals. François Chapdelaine, a member of its independent advisory committee, challenged that assessment, pointing to construction-price increases.
The committee had also warned that late changes to road budgets could leave tenders without bidders or produce bids above estimates. Its January report recorded 77 project postponements linked to internal labour pressure during 2022.
The unresolved issue is therefore both financial and operational. The province has identified more maintenance than its existing schedule can accommodate, while 2027 must now absorb work carried over from 2026.