One Tracker Found 47 Troubled US Data Centres, Another Found 75 in Just One Quarter

Two trackers studying setbacks in America’s data-centre boom are reporting sharply different counts, exposing a gap between headline project totals and the information investors need to assess whether announced AI computing capacity will actually be built.

RegLayer identified at least 47 major US data-centre projects delayed, withdrawn, or blocked during 2026, according to a Financial Times investigation. Meanwhile, Data Center Watch, a project of research firm 10a Labs, recorded at least 75 projects disrupted by local opposition in the first quarter alone.

Those developments carried approximately $130 billion in proposed investment value.

Selkirk Copper Mines — sponsored Sponsored · Selkirk Copper Mines

RegLayer’s count, as reported by the FT, concerns major developments. Data Center Watch focuses on projects affected by community opposition, including permitting challenges, moratoriums, and withdrawals.

Data Center Watch also distinguishes between projects blocked and projects delayed. The former includes proposals withdrawn following opposition, while the latter can remain active despite missing their original timelines.

The group’s first-quarter findings were already public in June. Its second-quarter report identified 45 projects worth nearly $68 billion blocked or delayed between April and June, down from 75 in the preceding quarter.

The second-quarter report also cited continuing opposition to projects previously disrupted, making it inappropriate to treat the quarterly counts as 120 unique failed developments.

Cambria Gold Mines — sponsored Sponsored · Cambria Gold Mines

The numbers instead point to a more consequential distinction between a proposed facility and one capable of supplying paying customers with computing capacity.

Investment forecasts can include projects at substantially different stages, from preliminary announcements to permitted construction and completed facilities awaiting electricity. A setback recorded by an opposition tracker does not, by itself, establish how much computing capacity will be unavailable, for how long, or whether customers have contractual remedies.

Bernstein Research estimates that approximately 35% of the planned US data-centre pipeline is credible, according to the FT.

Electricity regulators are attempting to establish more consistent information on one part of the development pipeline. On October 9, the Federal Energy Regulatory Commission approved a large-load registry proposed by PJM Interconnection, which operates the grid serving much of the Mid-Atlantic and Midwest.

The registry covers large electricity users meeting a 50-megawatt threshold and will gather information including expected service dates and power requirements. FERC rejected separate proposed provisions governing service and curtailment.

The registry will not reconcile the competing national project tallies. That would require comparable project identities, development stages, power-connection dates, and measures of planned capacity.

Until those details are available, the 47 and 75 counts document disruptions but establish neither the share of projects that will fail nor how much of America’s advertised AI infrastructure pipeline will reach operation.

Information for this briefing was found via the sources and the companies mentioned. The author has no securities or affiliations related to this organization. Not a recommendation to buy or sell. Always do additional research and consult a professional before purchasing a security. The author holds no licenses.

Leave a Reply

Video Articles

Similar Gold Mines Are Valued 10X Higher. Why Not This One? | JW Dumont – Granada Gold Mine

The US Interest Bill Gold Can’t Ignore | Peter Grandich

Gold Wins When the Fed Sacrifices the Dollar | Jay Martin

Recommended

First Majestic Produces 3.4 Million Ounces of Silver in Q3 2026, Jerritt Canyon Restart Remains on Track

Altamira Gold Drills 134 Metres of 0.5 g/t Gold at Maria Bonita, Hole Ends in Mineralization

Related News

AI Is Consuming Power at Record Rate, Data Centers to Make Up Demand Growth

The US electric utility industry is forecasting a significant increase in electricity demand driven by...

Thursday, April 11, 2024, 03:40:00 PM

Alberta Data Centre Demand Could Lift Wholesale Electricity Prices

Alberta’s first hyperscale artificial intelligence project has exposed a timing gap in the province’s strategy...

Monday, July 20, 2026, 10:34:00 AM

Are Data Centers Becoming the New AI Bubble?

The most revealing test of the artificial intelligence boom may not be whether demand for...

Tuesday, July 21, 2026, 01:16:00 PM

Despite Climate Pledges, Data Centers Set to Drive Natural Gas Boom

S&P projects up to 6 bcf/d increase as AI boom strains power grid...
Thursday, October 31, 2024, 02:50:00 PM

OpenAI Abandons Own Data Center Plans, Reshuffles Stargate Leadership as Financing Falters

OpenAI has scrapped plans to build and own its data centers, pivoting instead to renting...

Tuesday, March 17, 2026, 12:04:00 PM