Endeavour Silver Sees Initial Capital Costs Jump 22% At Terronera

Endeavour Silver (TSX: EDR) has seen expected costing at its Terronera project under development rise dramatically. The firm this morning provided a progress update to the project, indicating that expected costing has risen over 22%.

Total direct and indirect costing at the project has risen from $271 million to $332 million, a jump of $61 million. The increase was split between direct cost increases of $31.8 million and indirect cost increases of $29.2 million, which was partially offset by a decrease in contingencies.

On the direct side of things, mining costs have increased by $16 million, which is largely attributed to the delays in commissioning the lower platform facilities, as well as increased waste rock disposal costs. The processing plant is also over budget by $13.2 million, which is blamed on additional blasting required for lower platform excavation, extra work for expediting steel fabrication, and extra materials for the tailings facility, among other items.

Cambria Gold Mines — sponsored Sponsored · Cambria Gold Mines

Indirect costs meanwhile increased due to additional engineering, construction management, and the addition of several support buildings that were not originally planned, as well as a result of a larger workforce required than originally anticipated.

Development at Terronera is said to now be 89.4% complete, with Endeavour currently targeting early in Q2 for full system commissioning to begin on site. Operational guidance is slated to be released as construction approaches wet commissioning.

“Dry commissioning is advancing well on the Upper Platform and we’re completing final installations and the last of the punch list items. Our team’s efforts are concentrated on timely completion of the Lower Platform where structural steel is advancing to install the tailing filters. We’re focused on maintaining our construction schedule and momentum to have Terronera ready for full commissioning in early Q2 2025,” commented Don Gray, COO of Endeavour Silver.

Endeavour Silver last traded at $5.85 on the TSX.


Information for this briefing was found via Sedar and the companies mentioned. The author has no securities or affiliations related to this organization. Not a recommendation to buy or sell. Always do additional research and consult a professional before purchasing a security. The author holds no licenses.

Video Articles

Gold Could Fall Further. Here’s What I’m Buying | Rick Rule

Newmont Crushed Q3. So Why Did the Stock Fall?

Governments Bet on Critical Minerals While Investors Panic | John Passalacqua – First Phosphate

Recommended

First Majestic Hits 4.24 g/t Gold Over 48.8 Metres at Saval as Jerritt Canyon Restart Advances

First Majestic Lifts Q3 Revenue 38% to US$394.1 Million on Higher Silver Prices

Related News

Endeavour Silver Q4 Earnings: Market Loves The Results

Three weeks ago we had a request to cover Endeavour Silver’s (TSX: EDR) fourth quarter...

Sunday, March 16, 2025, 12:25:00 PM

Why Silver Lags Even at $41 | Dan Dickson – Endeavor Silver Corp

Dan Dickson, CEO of Endeavour Silver (NYSE: EXK) (TSX: EDR), breaks down what’s behind silver’s...

Friday, September 19, 2025, 02:14:00 PM

Endeavour Silver Produces 3.6 Million Silver Equivalent Ounces in Q3 as Blockade and Mill Repair Weigh on Throughput

Endeavour Silver (TSX: EDR) produced 3.6 million silver equivalent ounces in the third quarter of...

Friday, October 9, 2026, 09:29:59 AM

Endeavour Silver Q1 Earnings: Terronera Remains The Focus

The theory goes that right now should be one of the best times to be...

Saturday, May 31, 2025, 12:22:00 PM

Endeavour Silver Intersects 1,611 G/T Silver Equivalent Over 1.0 Metre At Bolañitos Mine

Endeavour Silver Corp. (TSX: EDR) announced today the latest drill results from the Bolañitos Mine...

Thursday, May 20, 2021, 09:26:00 AM