Endeavour Silver Sees Initial Capital Costs Jump 22% At Terronera

Endeavour Silver (TSX: EDR) has seen expected costing at its Terronera project under development rise dramatically. The firm this morning provided a progress update to the project, indicating that expected costing has risen over 22%.

Total direct and indirect costing at the project has risen from $271 million to $332 million, a jump of $61 million. The increase was split between direct cost increases of $31.8 million and indirect cost increases of $29.2 million, which was partially offset by a decrease in contingencies.

On the direct side of things, mining costs have increased by $16 million, which is largely attributed to the delays in commissioning the lower platform facilities, as well as increased waste rock disposal costs. The processing plant is also over budget by $13.2 million, which is blamed on additional blasting required for lower platform excavation, extra work for expediting steel fabrication, and extra materials for the tailings facility, among other items.

Selkirk Copper Mines — sponsored Sponsored · Selkirk Copper Mines

Indirect costs meanwhile increased due to additional engineering, construction management, and the addition of several support buildings that were not originally planned, as well as a result of a larger workforce required than originally anticipated.

Development at Terronera is said to now be 89.4% complete, with Endeavour currently targeting early in Q2 for full system commissioning to begin on site. Operational guidance is slated to be released as construction approaches wet commissioning.

“Dry commissioning is advancing well on the Upper Platform and we’re completing final installations and the last of the punch list items. Our team’s efforts are concentrated on timely completion of the Lower Platform where structural steel is advancing to install the tailing filters. We’re focused on maintaining our construction schedule and momentum to have Terronera ready for full commissioning in early Q2 2025,” commented Don Gray, COO of Endeavour Silver.

Endeavour Silver last traded at $5.85 on the TSX.


Information for this briefing was found via Sedar and the companies mentioned. The author has no securities or affiliations related to this organization. Not a recommendation to buy or sell. Always do additional research and consult a professional before purchasing a security. The author holds no licenses.

Video Articles

Red Cloud Fall Mining Showcase 2026 | Day 2

More Gold Without a Bigger Upfront Bill? | Keith Boyle – New Found Gold

The Red Cloud Fall Mining Showcase 2026 | Day 1

Recommended

First Majestic Lifts Q3 Revenue 38% to US$394.1 Million on Higher Silver Prices

Meghan Markle’s Half-Brother Submitted Evidence Against Their Father, But Now Faces Philippine Police Scrutiny

Related News

Max Resource Corp Enters Definitive Cooperation Agreement With Endeavour Silver

Max Resource Corp (TSXV: MXR) has made it official. The firm this morning revealed it...

Monday, March 21, 2022, 07:44:07 AM

Endeavour Silver Q3 Earnings: On The Upswing

It’s been an absolute slugfest for shareholders. But things are starting to look up for...

Sunday, November 23, 2025, 11:27:00 AM

Endeavour Silver Announces Financing To Fund Pitarrilla Project Purchase

Endeavour Silver (TSX: EDR) is looking to raise funds. The firm last night after the...

Wednesday, March 16, 2022, 07:38:51 AM

Endeavour Silver Cuts Guanaceví Throughput 45% After Ball Mill Failure

Endeavour Silver (TSX: EDR) has cut processing capacity at its Guanaceví mine by nearly half...

Tuesday, September 22, 2026, 08:49:16 AM

Endeavour Silver Reports Q1 Production Decline With 1.9 Million Silver Equivalent Ounces Produced

Endeavour Silver (TSX: EDR) saw a decline in its first quarter production on a year...

Wednesday, April 9, 2025, 10:04:00 AM