Endeavour Silver Sees Initial Capital Costs Jump 22% At Terronera

Endeavour Silver (TSX: EDR) has seen expected costing at its Terronera project under development rise dramatically. The firm this morning provided a progress update to the project, indicating that expected costing has risen over 22%.

Total direct and indirect costing at the project has risen from $271 million to $332 million, a jump of $61 million. The increase was split between direct cost increases of $31.8 million and indirect cost increases of $29.2 million, which was partially offset by a decrease in contingencies.

On the direct side of things, mining costs have increased by $16 million, which is largely attributed to the delays in commissioning the lower platform facilities, as well as increased waste rock disposal costs. The processing plant is also over budget by $13.2 million, which is blamed on additional blasting required for lower platform excavation, extra work for expediting steel fabrication, and extra materials for the tailings facility, among other items.

Selkirk Copper Mines — sponsored Sponsored · Selkirk Copper Mines

Indirect costs meanwhile increased due to additional engineering, construction management, and the addition of several support buildings that were not originally planned, as well as a result of a larger workforce required than originally anticipated.

Development at Terronera is said to now be 89.4% complete, with Endeavour currently targeting early in Q2 for full system commissioning to begin on site. Operational guidance is slated to be released as construction approaches wet commissioning.

“Dry commissioning is advancing well on the Upper Platform and we’re completing final installations and the last of the punch list items. Our team’s efforts are concentrated on timely completion of the Lower Platform where structural steel is advancing to install the tailing filters. We’re focused on maintaining our construction schedule and momentum to have Terronera ready for full commissioning in early Q2 2025,” commented Don Gray, COO of Endeavour Silver.

Endeavour Silver last traded at $5.85 on the TSX.


Information for this briefing was found via Sedar and the companies mentioned. The author has no securities or affiliations related to this organization. Not a recommendation to buy or sell. Always do additional research and consult a professional before purchasing a security. The author holds no licenses.

Video Articles

The Red Cloud Fall Mining Showcase 2026 | Day 1

Can an Old Irish Mine Recover the Silver It Left Behind? | Julian Vickers – Northmin Corporation

Is Gold at $4,000 a Buy Zone or a Breakdown? | David Morgan

Recommended

Police Contain ‘Active Threat’ at University of Toronto Mississauga Residence

McLaren Resources Launches Satellite Targeting Program Across Three Timmins Area Gold Properties

Related News

Endeavour Silver Cuts GuanacevĂ­ Throughput 45% After Ball Mill Failure

Endeavour Silver (TSX: EDR) has cut processing capacity at its GuanacevĂ­ mine by nearly half...

Tuesday, September 22, 2026, 08:49:16 AM

Endeavour Silver Intersects 2,914 G/T Silver Equivalent Over 0.89 Metre At Parral Project

Endeavour Silver Corp. (TSX: EDR) announced today the latest drill results from the ongoing exploration...

Thursday, December 16, 2021, 12:36:00 PM

Endeavour Silver Produces 3.6 Million Silver Equivalent Ounces in Q3 as Blockade and Mill Repair Weigh on Throughput

Endeavour Silver (TSX: EDR) produced 3.6 million silver equivalent ounces in the third quarter of...

Friday, October 9, 2026, 09:29:59 AM

Endeavour Silver Expects 2022 Silver Equivalent Production At 6.7 – 7.6 Million Ounces

Endeavour Silver Corp. (TSX: EDR) shared today its production and operational guidances for 2022. The...

Thursday, January 20, 2022, 12:33:00 PM

Endeavour Silver Reports Commercial Production At Terronera

Endeavour Silver (TSX: EDR) has finally achieved commercial production at their new Terronera mine in...

Thursday, October 16, 2025, 08:39:18 AM