Endeavour Silver Sees Initial Capital Costs Jump 22% At Terronera

Endeavour Silver (TSX: EDR) has seen expected costing at its Terronera project under development rise dramatically. The firm this morning provided a progress update to the project, indicating that expected costing has risen over 22%.

Total direct and indirect costing at the project has risen from $271 million to $332 million, a jump of $61 million. The increase was split between direct cost increases of $31.8 million and indirect cost increases of $29.2 million, which was partially offset by a decrease in contingencies.

On the direct side of things, mining costs have increased by $16 million, which is largely attributed to the delays in commissioning the lower platform facilities, as well as increased waste rock disposal costs. The processing plant is also over budget by $13.2 million, which is blamed on additional blasting required for lower platform excavation, extra work for expediting steel fabrication, and extra materials for the tailings facility, among other items.

Indirect costs meanwhile increased due to additional engineering, construction management, and the addition of several support buildings that were not originally planned, as well as a result of a larger workforce required than originally anticipated.

Development at Terronera is said to now be 89.4% complete, with Endeavour currently targeting early in Q2 for full system commissioning to begin on site. Operational guidance is slated to be released as construction approaches wet commissioning.

“Dry commissioning is advancing well on the Upper Platform and we’re completing final installations and the last of the punch list items. Our team’s efforts are concentrated on timely completion of the Lower Platform where structural steel is advancing to install the tailing filters. We’re focused on maintaining our construction schedule and momentum to have Terronera ready for full commissioning in early Q2 2025,” commented Don Gray, COO of Endeavour Silver.

Endeavour Silver last traded at $5.85 on the TSX.


Information for this briefing was found via Sedar and the companies mentioned. The author has no securities or affiliations related to this organization. Not a recommendation to buy or sell. Always do additional research and consult a professional before purchasing a security. The author holds no licenses.

Leave a Reply

Video Articles

Endeavour Mining Q1 Earnings: Cash Flow Is King

G Mining Oko West Feasibility: Move Fast, Break.. Nothing?

New Gold Q1 Earnings: What’s Behind The Market’s Surprising Reaction?

Recommended

First Majestic Posts Record Cash Flows In Q1 As Production Costs Fall

Brazil Potash Secures Funding In Support Of US$2.5 Billion Autozales Project

Related News

Endeavour Silver Records Revenue Decline, Net Loss After Withholding 1.6 Million Silver Equivalent Ounces For Future Sale

Endeavour Silver Corp. (TSX: EDR) shared on Tuesday its financial results for Q2 2022. The...

Tuesday, August 9, 2022, 03:02:00 PM

Endeavour Silver Produces 7.6 Million Silver Equivalent Ounces in 2024

Endeavour Silver (TSX: EDR) reported this morning that in the fourth quarter it managed to...

Thursday, January 9, 2025, 09:19:35 AM

Endeavour Silver Produces 2.0 Million Silver Equivalent Ounces In Q1 2022

Endeavour Silver Corp. (TSX: EDR) shared this morning its production update for Q1 2022. The...

Monday, April 11, 2022, 09:48:00 AM

VanGold Acquires El Cubo Mine & Mill From Endeavour Silver For US$15.0 Million

VanGold Mining (TSXV: VGLD) announced that it has entered into a definitive agreement with Endeavour...

Wednesday, March 17, 2021, 07:57:17 AM

Endeavour Silver Reports Q1 Production Decline With 1.9 Million Silver Equivalent Ounces Produced

Endeavour Silver (TSX: EDR) saw a decline in its first quarter production on a year...

Wednesday, April 9, 2025, 10:04:00 AM