Endeavour Silver Sees Initial Capital Costs Jump 22% At Terronera

Endeavour Silver (TSX: EDR) has seen expected costing at its Terronera project under development rise dramatically. The firm this morning provided a progress update to the project, indicating that expected costing has risen over 22%.

Total direct and indirect costing at the project has risen from $271 million to $332 million, a jump of $61 million. The increase was split between direct cost increases of $31.8 million and indirect cost increases of $29.2 million, which was partially offset by a decrease in contingencies.

On the direct side of things, mining costs have increased by $16 million, which is largely attributed to the delays in commissioning the lower platform facilities, as well as increased waste rock disposal costs. The processing plant is also over budget by $13.2 million, which is blamed on additional blasting required for lower platform excavation, extra work for expediting steel fabrication, and extra materials for the tailings facility, among other items.

Silver47 Exploration Inc. — sponsored Sponsored · Silver47 Exploration Inc.

Indirect costs meanwhile increased due to additional engineering, construction management, and the addition of several support buildings that were not originally planned, as well as a result of a larger workforce required than originally anticipated.

Development at Terronera is said to now be 89.4% complete, with Endeavour currently targeting early in Q2 for full system commissioning to begin on site. Operational guidance is slated to be released as construction approaches wet commissioning.

“Dry commissioning is advancing well on the Upper Platform and we’re completing final installations and the last of the punch list items. Our team’s efforts are concentrated on timely completion of the Lower Platform where structural steel is advancing to install the tailing filters. We’re focused on maintaining our construction schedule and momentum to have Terronera ready for full commissioning in early Q2 2025,” commented Don Gray, COO of Endeavour Silver.

Endeavour Silver last traded at $5.85 on the TSX.


Information for this briefing was found via Sedar and the companies mentioned. The author has no securities or affiliations related to this organization. Not a recommendation to buy or sell. Always do additional research and consult a professional before purchasing a security. The author holds no licenses.

Video Articles

Seabridge Loses KSM’s Substantially Started Status

This Gold Giant Got Crushed… Now It’s the Cheapest Major | Kinross Gold’s Q3 Earnings

Why I’m Still Bullish on Gold Below $3,900 | Wes Hanson – Thunder Gold

Recommended

Canadian Copper Step Out Drilling Returns 54.55 Metres of 0.80% Copper at Murray Brook

Epic Gold Delivers Maiden 279,000 Ounce Inferred Resource at Wilson Project

Related News

Endeavour Silver Trims Guanaceví Silver Guidance After Q3 Net Earnings Fall to US$26.4 Million

Endeavour Silver (TSX: EDR) posted third quarter revenue of US$184.5 million, down from US$212.1 million...

Tuesday, November 10, 2026, 09:07:08 AM

BMO Lifts Endeavour Silver’s Price Target Following Better Than Expected Q1 Results

On April 11th, Endeavour Silver Corp. (TSX: EDR) announced its first quarter of 2021 production...

Thursday, April 14, 2022, 11:24:00 AM

Endeavour Silver Reports Commercial Production At Terronera

Endeavour Silver (TSX: EDR) has finally achieved commercial production at their new Terronera mine in...

Thursday, October 16, 2025, 08:39:18 AM

Max Resource Corp Enters Definitive Cooperation Agreement With Endeavour Silver

Max Resource Corp (TSXV: MXR) has made it official. The firm this morning revealed it...

Monday, March 21, 2022, 07:44:07 AM

VanGold Acquires El Cubo Mine & Mill From Endeavour Silver For US$15.0 Million

VanGold Mining (TSXV: VGLD) announced that it has entered into a definitive agreement with Endeavour...

Wednesday, March 17, 2021, 07:57:17 AM