Endeavour Silver Sees Initial Capital Costs Jump 22% At Terronera

Endeavour Silver (TSX: EDR) has seen expected costing at its Terronera project under development rise dramatically. The firm this morning provided a progress update to the project, indicating that expected costing has risen over 22%.

Total direct and indirect costing at the project has risen from $271 million to $332 million, a jump of $61 million. The increase was split between direct cost increases of $31.8 million and indirect cost increases of $29.2 million, which was partially offset by a decrease in contingencies.

On the direct side of things, mining costs have increased by $16 million, which is largely attributed to the delays in commissioning the lower platform facilities, as well as increased waste rock disposal costs. The processing plant is also over budget by $13.2 million, which is blamed on additional blasting required for lower platform excavation, extra work for expediting steel fabrication, and extra materials for the tailings facility, among other items.

Indirect costs meanwhile increased due to additional engineering, construction management, and the addition of several support buildings that were not originally planned, as well as a result of a larger workforce required than originally anticipated.

Development at Terronera is said to now be 89.4% complete, with Endeavour currently targeting early in Q2 for full system commissioning to begin on site. Operational guidance is slated to be released as construction approaches wet commissioning.

“Dry commissioning is advancing well on the Upper Platform and we’re completing final installations and the last of the punch list items. Our team’s efforts are concentrated on timely completion of the Lower Platform where structural steel is advancing to install the tailing filters. We’re focused on maintaining our construction schedule and momentum to have Terronera ready for full commissioning in early Q2 2025,” commented Don Gray, COO of Endeavour Silver.

Endeavour Silver last traded at $5.85 on the TSX.


Information for this briefing was found via Sedar and the companies mentioned. The author has no securities or affiliations related to this organization. Not a recommendation to buy or sell. Always do additional research and consult a professional before purchasing a security. The author holds no licenses.

Video Articles

Silver @ $36 & We’re Still 200M Oz Short | Paul Andre Huet – Americas Gold and Silver

Gold’s Wild Bull Run: Are Markets About to Break? | Mike McGlone

First Majestic Silver: The Santa Elena Mine

Recommended

Goliath Resources Closes Out Funding Round With Total Gross Proceeds Of $27.1 Million

Silver47 Kickstarts 4,000 Metre Drill Campaign At Red Mountain Project

Related News

Endeavour Silver’s 24% Output Drop Drives $17.3M Loss, Cost Pressures Mount

Endeavour Silver Corp. (TSX: EDR) reported mixed financial and operational performance for Q3 2024, shaped...

Tuesday, November 5, 2024, 09:09:24 AM

Endeavour Silver Q4 Earnings: Market Loves The Results

Three weeks ago we had a request to cover Endeavour Silver’s (TSX: EDR) fourth quarter...

Sunday, March 16, 2025, 12:25:00 PM

Endeavour Silver Records Revenue Decline, Net Loss After Withholding 1.6 Million Silver Equivalent Ounces For Future Sale

Endeavour Silver Corp. (TSX: EDR) shared on Tuesday its financial results for Q2 2022. The...

Tuesday, August 9, 2022, 03:02:00 PM

Endeavour Silver: BMO Lowers Price Target Following Guidance

Thursday morning Endeavour Silver (TSX: EDR) released their 2021 production guidance for 2021, guiding towards...

Sunday, January 31, 2021, 02:41:00 PM

Endeavour Silver Expects 2022 Silver Equivalent Production At 6.7 – 7.6 Million Ounces

Endeavour Silver Corp. (TSX: EDR) shared today its production and operational guidances for 2022. The...

Thursday, January 20, 2022, 12:33:00 PM