Endeavour Silver Sees Initial Capital Costs Jump 22% At Terronera

Endeavour Silver (TSX: EDR) has seen expected costing at its Terronera project under development rise dramatically. The firm this morning provided a progress update to the project, indicating that expected costing has risen over 22%.

Total direct and indirect costing at the project has risen from $271 million to $332 million, a jump of $61 million. The increase was split between direct cost increases of $31.8 million and indirect cost increases of $29.2 million, which was partially offset by a decrease in contingencies.

On the direct side of things, mining costs have increased by $16 million, which is largely attributed to the delays in commissioning the lower platform facilities, as well as increased waste rock disposal costs. The processing plant is also over budget by $13.2 million, which is blamed on additional blasting required for lower platform excavation, extra work for expediting steel fabrication, and extra materials for the tailings facility, among other items.

Granada Gold Mine Inc. — sponsored Sponsored · Granada Gold Mine Inc.

Indirect costs meanwhile increased due to additional engineering, construction management, and the addition of several support buildings that were not originally planned, as well as a result of a larger workforce required than originally anticipated.

Development at Terronera is said to now be 89.4% complete, with Endeavour currently targeting early in Q2 for full system commissioning to begin on site. Operational guidance is slated to be released as construction approaches wet commissioning.

“Dry commissioning is advancing well on the Upper Platform and we’re completing final installations and the last of the punch list items. Our team’s efforts are concentrated on timely completion of the Lower Platform where structural steel is advancing to install the tailing filters. We’re focused on maintaining our construction schedule and momentum to have Terronera ready for full commissioning in early Q2 2025,” commented Don Gray, COO of Endeavour Silver.

Endeavour Silver last traded at $5.85 on the TSX.


Information for this briefing was found via Sedar and the companies mentioned. The author has no securities or affiliations related to this organization. Not a recommendation to buy or sell. Always do additional research and consult a professional before purchasing a security. The author holds no licenses.

Video Articles

This Copper Mine Costs 1/6 to Restart | SSR Mining X Roxmore

Why Cambria Hit Pause on Its Massive Copper-Gold Spinout

Can Gold Rescue Washington From Its Debt Trap? | Andy Schectman – Miles Franklin

Recommended

Mercado Minerals Lengthens El Triunfo Vein by 190 Metres, Readies 1,500-Metre Zamora Drill Program

Blue Jay Gold Signs Ocean Partners Deal to Ship Steller Stockpiles Through 2027

Related News

Endeavour Silver To Acquire Minera Kolpa For $145 Million

Endeavour Silver (TSX: EDR) is expanding into the country of Peru as it looks to...

Tuesday, April 1, 2025, 08:55:43 AM

Endeavour Silver: BMO Reiterates Price Target Despite Big Production Beat

Endeavour Silver Corp. (TSX: EDR) last week reported its second-quarter production results. The company announced...

Thursday, July 14, 2022, 02:25:00 PM

Endeavour Silver Reports Q1 Production Decline With 1.9 Million Silver Equivalent Ounces Produced

Endeavour Silver (TSX: EDR) saw a decline in its first quarter production on a year...

Wednesday, April 9, 2025, 10:04:00 AM

Endeavour Silver Expects 2022 Silver Equivalent Production At 6.7 – 7.6 Million Ounces

Endeavour Silver Corp. (TSX: EDR) shared today its production and operational guidances for 2022. The...

Thursday, January 20, 2022, 12:33:00 PM

Endeavour Silver Announces Financing To Fund Pitarrilla Project Purchase

Endeavour Silver (TSX: EDR) is looking to raise funds. The firm last night after the...

Wednesday, March 16, 2022, 07:38:51 AM