Endeavour Silver Sees Initial Capital Costs Jump 22% At Terronera

Endeavour Silver (TSX: EDR) has seen expected costing at its Terronera project under development rise dramatically. The firm this morning provided a progress update to the project, indicating that expected costing has risen over 22%.

Total direct and indirect costing at the project has risen from $271 million to $332 million, a jump of $61 million. The increase was split between direct cost increases of $31.8 million and indirect cost increases of $29.2 million, which was partially offset by a decrease in contingencies.

On the direct side of things, mining costs have increased by $16 million, which is largely attributed to the delays in commissioning the lower platform facilities, as well as increased waste rock disposal costs. The processing plant is also over budget by $13.2 million, which is blamed on additional blasting required for lower platform excavation, extra work for expediting steel fabrication, and extra materials for the tailings facility, among other items.

Selkirk Copper Mines — sponsored Sponsored · Selkirk Copper Mines

Indirect costs meanwhile increased due to additional engineering, construction management, and the addition of several support buildings that were not originally planned, as well as a result of a larger workforce required than originally anticipated.

Development at Terronera is said to now be 89.4% complete, with Endeavour currently targeting early in Q2 for full system commissioning to begin on site. Operational guidance is slated to be released as construction approaches wet commissioning.

“Dry commissioning is advancing well on the Upper Platform and we’re completing final installations and the last of the punch list items. Our team’s efforts are concentrated on timely completion of the Lower Platform where structural steel is advancing to install the tailing filters. We’re focused on maintaining our construction schedule and momentum to have Terronera ready for full commissioning in early Q2 2025,” commented Don Gray, COO of Endeavour Silver.

Endeavour Silver last traded at $5.85 on the TSX.


Information for this briefing was found via Sedar and the companies mentioned. The author has no securities or affiliations related to this organization. Not a recommendation to buy or sell. Always do additional research and consult a professional before purchasing a security. The author holds no licenses.

Video Articles

This Copper Mine Costs 1/6 to Restart | SSR Mining X Roxmore

Why Cambria Hit Pause on Its Massive Copper-Gold Spinout

Can Gold Rescue Washington From Its Debt Trap? | Andy Schectman – Miles Franklin

Recommended

Mercado Minerals Lengthens El Triunfo Vein by 190 Metres, Readies 1,500-Metre Zamora Drill Program

Blue Jay Gold Signs Ocean Partners Deal to Ship Steller Stockpiles Through 2027

Related News

Endeavour Silver Beats Guidance With 8.3 Million Silver Equivalent Ounces Produced In 2021

Endeavour Silver (TSX: EDR) this morning released its fourth quarter and full year 2021 financial...

Thursday, March 10, 2022, 08:22:06 AM

Pitarrilla: One of the World’s Largest Undeveloped Silver Assets? | Endeavour Silver with Dan Dickson

In this interview at the Precious Metals Summit 2024, Dan Dickson, CEO & Director of...

Friday, September 20, 2024, 01:45:00 PM

Endeavour Silver Says Terronera Blockade Removed, Operations Resume Monday

Endeavour Silver (TSX: EDR) said late Sunday that a blockade that shut down its flagship...

Monday, August 24, 2026, 09:41:18 AM

Endeavour Silver Grows Production 88% In Q3, Records Net Loss On Derivative Contracts

Endeavour Silver (TSX: EDR) posted their third quarter financial results this morning, highlighted by revenue...

Friday, November 7, 2025, 08:51:00 AM

Endeavour Silver Produces 2.0 Million Silver Equivalent Ounces In Q1 2022

Endeavour Silver Corp. (TSX: EDR) shared this morning its production update for Q1 2022. The...

Monday, April 11, 2022, 09:48:00 AM